Measure G & C Construction Updates

Measures G and C Construction Updates

Construction Zones and Impacts
April 1–Nov. 1, 2024

Smithwick Theatre Closed

New roof and laminated beams will be added to the Smithwick. Access to restrooms, Lot 1A and stairs from Lot 1 will be impacted.

    • The building will be fenced off and Lot 1A will be closed.
    • There will be no access to the two restrooms in the Smithwick. Nearest open restrooms are in the Campus Center.
    • There will be no direct access from Lot 1 as the stairs next to the Smithwick will be fenced.
    • When parking in Lot 1, please use the walking pathway to Lot 8 and enter the campus through the Lower Campus stairs. For parking lot locations, see campus map.

Library Restrooms Closed

The two restrooms inside the Library (3500) will be converted to all gender. The library will remain in use, but students who require a distraction-free studying space will be made aware of alternate rooms (LRC/STEM Center, etc.) that they can use as well as the locations of the nearest restrooms.

8500 Restrooms Closed

The two restrooms outside the Veterinary Technology classroom (8507) will be converted to all gender.  Restrooms on the next floor (8600) will be open.

What are Measures G and C?

Measure G


On March 3, 2020, voters in the Foothill-De Anza Community College District’s service area approved by a 58.8% margin an $898 million general obligation bond measure to upgrade facilities preparing students/veterans for university transfer and careers in fields such as healthcare, nursing, technology, engineering/sciences; to upgrade and repair aging classrooms as well as labs for science, technology, engineering/math-related fields of instruction; and to acquire, construct, repair facilities, equipment and sites.

Measure C

On June 6, 2006, voters in the Foothill-De Anze Community College District's service area approved by a 65.69% margin a $490.8 million bond (Measure C).

These measures have and will enable the District to:

  • Upgrade electrical, heating, ventilation systems, fire/seismic safety;
  • Repair leaky roofs;
  • Improve disabled access;
  • Repair/expand classrooms;
  • Upgrade technology; and
  • Repair, construct, acquire, equip buildings, classrooms, libraries, sites, science/computer labs.

Read the 2018-19 annual Measure C report to the community.

For additional information, visit the Measure G and C Citizens' Bond Oversight Committee website.

Current Projects

Measure C Design Projects
  • Lot 5B Modular Removal/Additional Parking
  • B1900 MPOE
Measure C Construction Projects
  • B1100 Wheelchair Lift Replacement
  • B2500 Reroof
  • Veteran's Rotary Plaza
Measure C Construction Projects
  • District Office Building

Measure C Project Updates

Fall 2018

All major projects have been completed with the exception of the new district office building, which began construction January 2017. Estimated completion date is December 2018.

For location details, download construction map.

 

Campus Map with construction areas

 

 

 

building with flowers

Questions?
We're Here to Help!

Asha Jossis, Interim Supervisor, Finance and Administration 

650.949.7253


jossisasha@fhda.edu


Building 1900, Office 1909

Other Measure C Foothill Contacts
  • Bret Watson, VP of Finance and Administrative Services, 650.949.7364
  •  

 

Top